Construction progress of Castle-1 project by New Nordic - 05 March 2018
Castle-1 project
Overall construction progress 80%:
- Pouring concrete walls on the 8th floor completed
- Installing electric wiring and drain pipes on 8th floor
- Laying brick wall on the 6th floor
- Plastering on the 4th floor