Construction progress of Castle-1 project by New Nordic - 16 January 2018
Castle-1 project
Overall construction progress 73%:
- Pouring concrete walls on the 8th floor
- Installing electric wiring and drain pipes on 7th floor
- Laying brick wall on the 3rd floor 99% progress
- Plastering on the 3rd floor