Construction progress of Castle-1 project by New Nordic - 16 July 2018
Castle-1 project
Overall construction progress 99%:
- Tiling bathrooms on the 5th floor
- Plastering on the 6th floor
- Ceiling paint work on the 2nd floor
- Installing water drainage on the 8th floor