Construction progress of Castle-1 project by New Nordic - 26 February 2018
Castle-1 project
Overall construction progress 79%:
- Pouring concrete walls on the 8th floor
- Installing electric wiring and drain pipes on 8th floor
- Laying brick wall on the 5th floor
- Plastering on the 3rd floor