Construction progress of Castle-2 project by New Nordic - 11 September 2018
Castle-2 project
Overall construction progress 67%:
- Installing the precast walls on the 4th floor
- Laying brick wall on 3rd and 4th floors
- Interior plastering on 1st floor
- Installing electric system on 3rd floor


