Construction progress of Castle-2 project by New Nordic - 13 November 2018
Castle-2 project
Overall construction progress 75%:
- Installing the precast walls on the 8th floor
- Laying brick wall on 6th floor
- Interior plastering on on 5th floor
- Installing electric system on 6th and 7th floor