Construction progress of Club-3 project by New Nordic - 18 January 2018
Club-3 project
Overall construction progress 38%:
- Making steel poles for the 6th floor completed
- Plastering on the 2nd floor completed
- Laying brick wall on the 4th floor
- Installing electric wiring and drain pipes on the 3rd floor
- Setting scaffolding on the 6th floor