Construction progress of Club-3 project by New Nordic - 24 October 2018
Club-3 project
Overall construction progress 85%:
- Laying tiles in bathrooms on 7th floor completed
- Installing wiring on 7th floor completed
- Exterior plastering in progress
- Interior plastering on the 7th floor
- Ceiling on the 7th floor
- Installing water drains on 7th floor