Construction progress of Club-3 project by New Nordic - 25 July 2018
Club-3 project
Overall construction progress 73%:
- Laying tiles in bathrooms on 5th floor
- Installing wiring and drains on 7th floor
- Plastering on the 7th floor completed
- Ceiling on the 4th floor