Construction progress of Club-3 project by New Nordic - 28 February 2018
Club-3 project
Overall construction progress 44%:
- Pouring concrete on 7th floor completed
- Plastering on the 4th floor
- Laying brick wall on the 5th floor
- Installing drains and electric wiring on 4th floor