Construction progress of Coral Beach project by New Nordic - 08 March 2018
Coral Beach Chumphon project
Overall construction progress 75%:
- Installing tiles on the roof
- Laying brick wall on the 4th floor
- Plastering on the 3rd floor
- Installing wiring and drains on the 2nd floor