Construction progress of Coral Beach project by New Nordic - 22 February 2018
Coral Beach Chumphon project
Overall construction progress 70%:
- Making steel frame for the roof
- Laying brick wall on the 4th floor
- Plastering on the 3rd floor
- Installing wiring and drains on the 2nd floor
![Coral project construction update 22.02.18 Coral project construction update 22.02.18](/pictures/news/thumbnails/coral-220218.jpg)
![Coral project construction update 22.02.18 Coral project construction update 22.02.18](/pictures/news/thumbnails/coral-220218-1.jpg)
![Coral project construction update 22.02.18 Coral project construction update 22.02.18](/pictures/news/thumbnails/coral-220218-2.jpg)