Construction progress of Trend-7 project by New Nordic - 07 February 2018
Trend-7 project
Overall construction progress 54%:
- Making steel frame for the roof completed
- Tiling apartments’ bathrooms on the 5th floor
- Laying brick wall on the 6th floor completed
- Plastering on the 5th floor completed
- Installing electric wiring and drains on the 6th floor