Construction progress of Trend-7 project by New Nordic - 07 March 2018
Trend-7 project
Overall construction progress 61%:
- Install the roof tiles completed
- Tiling apartments’ bathrooms on the 5th floor completed
- Laying brick wall on the 7th floor completed
- Plastering on the 7th floor