Construction progress of Trend-7 project by New Nordic - 15 August 2018
Trend-7 project
Overall construction progress 87%:
- Installing electric wiring on 7th floor
- Interior painting in progress
- Installing air conditioners
- Installing sanitary ware on 7th floor