Construction progress of Trend-7 project by New Nordic - 26 September 2018
Trend-7 project
Overall construction progress 93%:
- Installing electric wiring on 7th floor
- Tiling in rooms is completed
- Installing air conditioners
- Installing sanitary ware on 7th floor
- Installing UPVC windows on 6th and 7th floors


