Construction progress of Trend-7 project by New Nordic - 30 November 2017
Trend-7 project
Overall construction progress 40%:
- Pouring concrete on 7th floor completed
- Laying brick wall on the 5th floor
- Plastering on the 4th floor
- Installing electric wiring and drains on the 5th floor