Construction progress of Club-3 project by New Nordic - 24 January 2018
Club-3 project
Overall construction progress 39%:
- Making steel frame for the 6th floor
- Plastering on the 3rd floor
- Laying brick wall on the 4th floor
- Installing electric wiring and drain pipes on the 3rd floor