Construction progress of Trend-7 project by New Nordic - 24 January 2018
Trend-7 project
Overall construction progress 50%:
- Making steel frame for the roof
- Tiling apartments’ bathrooms on the 4th floor
- Laying brick wall on the 6th floor
- Plastering on the 5th floor
- Installing electric wiring and drains on the 6th floor