Construction progress of Club-3 project by New Nordic - 21 February 2018
Club-3 project
Overall construction progress 43%:
- Making steel frame on 7th floor
- Plastering on the 3rd floor completed
- Laying brick wall on the 4th floor
- Installing drains and electric wiring on 4th floor