Construction progress of Trend-7 project by New Nordic - 21 February 2018
Trend-7 project
Overall construction progress 58%:
- Install the roof tiles
- Tiling apartments’ bathrooms on the 5th floor
- Laying brick wall on the 7th floor
- Plastering on the 6th floor
- Installing electric wiring and drains on the 6th floor